By: Susan Peterson, M.B.A., PMP
Copyright 2010, Susan Peterson, All Rights Reserved
It may not seem like you’re signing up for project management when you volunteer for a board of directors or for a committee chair position. Maybe it’s your child’s parent-teacher organization, a homeowners’ association board, or a community group. However, managing volunteer activities can be one of the most challenging, rewarding, and frustrating project management assignments that you will ever have.
When a volunteer organization does not perform acceptably, someone will say, “Well, what can you expect from a bunch of volunteers?” This attitude is nothing but an excuse in disguise. At the very least, this question sets the expectation that any volunteer project must be a second-rate, half-hearted effort. Yet a great many successful projects only get accomplished because of a dedicated, competent group of volunteers. On more than one occasion, my volunteer teams and I have agreed that no one could pay us enough money to compensate us adequately for what we have volunteered to do!
So what’s a project manager to do when the team is loosely organized and can leave whenever the “going gets tough”? First of all, the team needs to determine what the target goal(s) of the effort are (sound familiar?). In a volunteer situation this effort has special challenges in that each individual has his/her own unique perspective on the situation and the desired outcomes. Therefore, it is also necessary to determine why each person volunteered to be a part of the effort. The diverse reasons for volunteering yield different attitudes toward the project as a whole and toward the “work ethic” that is exhibited. Some possible reasons why people volunteer include the following:
• Belief in the cause or role of the volunteer organization. These folks will generally work hard, but the project management challenge is to keep them focused and moving in a single direction.
• Status. The volunteer organization has a prestigious image so participation of any nature will look good on a resume. These people want “visibility”.
• Networking. These volunteers only want to associate with someone who can do something for them.
• Intimidation. Someone badgered the person into volunteering. These folks are generally “short timers”.
There are a number of considerations to address when managing a volunteer project team. Since everyone on the team has many other priorities, the tasks and deliverables should be defined as small, highly tangible efforts. Early and frequent accomplishments keep people energized even when the project is lengthy. Focused use of email and “virtual” meetings can eliminate many face-to-face meetings. When there are meetings, input should be solicited for an agenda that is circulated in advance. Of course, the agenda should be followed to avoid the volunteer “trap” of multiple tangents and non-productive meetings. It is especially critical to quickly learn each volunteer’s strengths and level of commitment. Some people sign up for everything and do nothing. Others don’t sign up at all but want to “be asked”. And then there are those rare “jewels” who sign up, do the work and bring in their deliverables on time.
I have been blessed to chair several volunteer efforts with talented people. It is to these special individuals and to those of you who do volunteer effectively that I dedicate this article.
Susan Peterson, M.B.A., PMP, is a consultant who manages diverse programs and projects in both the private and public sectors for individual organizations and consortia. She also conducts enterprise assessments of project portfolio management practices. Prior to establishing her consulting practice Susan led major efforts for Fortune 100 organizations throughout the United States. She teaches the Project Management Simulation capstone course as well as the Project Portfolio Management course in the University of California, San Diego, Project Management certificate program and is a member of the curriculum committee. She can be contacted at susanada@aol.com.
Showing posts with label human resources. Show all posts
Showing posts with label human resources. Show all posts
Wednesday, September 29, 2010
Friday, January 22, 2010
Matrix Management and Seniority

I found an interesting comment posted to one of my articles over on PM Hut. The commenter suggested that matrix management was responsible for stripping seniority from people within the organization. Matrix management is simply a way of organizing people and lines of communication. A quick trip to Wikipedia provides details. There is an expanded description in the PMBOK® Guide available for download at PMI.org. There are two basic forms of matrix management, but neither were intended to disrupt seniority or other aspects of employment.
In a pure matrix organization, employees are pooled in departments (e.g Engineering, Marketing, Finance). These employees are shared among the products and projects. This is often an advantageous configuration for professional development since during "bench" time (when not assigned to a project), employees have the benefit of working on internal projects to collaborate and increase skills. The functional managers are generally responsible for enhancing the talent pool through such opportunities or even direct professional development and training.
In the weak matrix organization, the organization may appear to be mostly a functional or hierarchical organization, however there are some coordinated projects, likely not requiring a full project manager.
As you can see, there is nothing intended to address seniority, pro or con. It is true some organizations find ways to abuse the matrix organization. These abuses may include overloading project team members with cross functional projects which are not properly coordinated or perhaps laying off people rather than providing bench time professional development.
If not properly managed, the matrix environment can also add extra overhead. With added lines of communication between the functional and the product/project managers, the time to reach decisions or communicate change may increase. Some structures include a resource manager with responsibility for tracking the projects resources and expediting personnel level decision. Properly managed, the projectized, strong matrix organization can provide excellent growth and career opportunities for all.
Sunday, October 18, 2009
Leadership Quotes - Part II (10/23)

Leading at a higher level is therefore a process. We define it as the process of achieving worthwhile results while acting with respect, care, and fairness for the well being of all involved.
In high performing organizations, everyone's energy is focused on not just one bottom line, but three bottom lines -- being the provider of choice, the employer of choice, and the investment of choice.
Ken Blanchard, Leading at a Higher Level
These three bottom lines are the trifecta for success. For some, they also become the triple constraints of success. Master all three and you will be successful. Master just one or two, and the journey to success will be longer and more difficult.
If you are the provider of choice and the investment of choice, assuming you are not within a very small and limited market, you will not have to worry about revenues or investment unless you cannot deliver the products or services because you are not an employer of choice and have difficulty keeping staff.
You may have the best staff in the work and have incredible business partners, but unless there is investment or sales, you will not be able to sustain them.
Here are a few simple things one can do to increase success in each of these areas.
Employer of Choice
I've always found that when seeking employment, if all other factors are equal, prospective employees will tend to join companies and work with teams where there are clear roles and responsibilities, and specific goals they know they can achieve. This gets them in the door. To maintain them, you need to develop a means by which you involve them in increasingly more challenging work so they can learn and grow. This will require some support of professional development in addition to ongoing mentoring and coaching. Obviously people are looking to be fairly compensated, so maintaining compensation around the norms for your industry and positions is important.
Provider of Choice
I've found another book from the Blanchard Group, Raving Fans has some of the best advice here -- find out what your customers want, then deliver plus one -- in other words, meet their needs and exceed their expectations.
Investment of Choice
Just as specific details help secure employees, a strong and detailed business plan, followed through, and supported by transparent reporting is one of the best ways I know to attract investors.
If you are the average company, it will be important to focus on all three. Obviously if you excel in some area (e.g. you've invented the next generation iPhone and everyone is going to need it), you may be able to garner more benefits in some areas which you can use to manage and invest in the others.
Through a cycle of continuous improvement in each of these areas, you will be able to take your project team or company to a higher level.
Saturday, August 15, 2009
The Vitality Curve -- Its Not for Everyone
Ever wonder why the "best and the brightest" aren't showing up on your project team? One distinct possibility is that your executive team and HR department hasn't heard of the Vitality Curve, a concept in use by GE and other highly successful companies. But this isn't a concept for everyone.
Jack Welch describes the concept in a 2005 article posted to Leadership Excellence Online. Its a very simple concept. On an ongoing basis, all employees are stack ranked. Names and details were passed up the chain to ensure execution. The bottom 10% was slated for an intervention -- redeployment or more often an exit, particularly if this was the second or third time you fell in that category. This opened up dollars to go out and seek better performers and bring them into the company.
All performance was divided into 20-70-10 percent categories. Top performers (1-10% of the top 20%) usually received extra bonuses, perks, or benefits. For example, after a number of service years and reaching a specified salary or management level, top performers were invited to join the ELFUN society. Perks included additional investment opportunities in exclusive funds and ELFUNs were often tapped for roles in leading charitable and public service projects.
The actions built the teams and skills in the process. As a new manager, its often easy to rank the performers. Once you've worked with a team for a while and understand the consequences, its a lot harder to do the ranking. But this honed management and differentiation skills by forcing leaders to take deep dives into performance, strategy, and accomplishment. These deep dives fuel continuous improvement since managers were always helping people find ways to improve.
These actions created a culture of high performance. "Rank and file" employees rarely thought about it and unless you were in one of the extreme groups, you might not even know it was happening. But the results were there. There was no concept of "dead wood" or "hanging in there until something better comes along". The company was filled with high performers and employees were motivated. But all this came at a financial cost.
To support the system, there was a complete HR system which included job descriptions, salary divisions, robust performance criteria, detailed annual performance appraisals, goals and objectives, and frequent performance feedback. There was also the cost of bonuses, rewards, and perks scaled to the organization. Execution was relentless and strategies, goals, and tactics had to be devised and reviewed. Every player had to know their position and was slotted into positions where they could be most successful. There was also no guarantee you would be in the same group forever -- re-evaluation was an ongoing process. It was an unswerving dedication to continuous improvement of people and in the process, the entire organization.
The results were obvious every day. People had fun in their jobs. As a manager and project manager, I never had to worry about who would show up to work -- good people were always there. And those costs I mentioned -- they were usually offset by improved productivity and corporate performance. The Vitality Curve helped the company go from good to great.
This didn't mean there weren't tough times. While GE has always been a financial powerhouse, the economic forces are often more powerful. But with a solid performing team, recovery from setbacks is quicker and there was an understanding that the work had to continue. The people chattering in the halls about coming layoffs and hard times were often those few in the bottom 10% or those headed in that direction.
So while this might not be a concept for everyone, the GE vitality curve is a must for devotees of continuous improvement and high performing teams. If you are working on a long term (e.g. 5 year) project or program, you may want to consider starting a grass roots version to see if your team improves.
Jack Welch describes the concept in a 2005 article posted to Leadership Excellence Online. Its a very simple concept. On an ongoing basis, all employees are stack ranked. Names and details were passed up the chain to ensure execution. The bottom 10% was slated for an intervention -- redeployment or more often an exit, particularly if this was the second or third time you fell in that category. This opened up dollars to go out and seek better performers and bring them into the company.
All performance was divided into 20-70-10 percent categories. Top performers (1-10% of the top 20%) usually received extra bonuses, perks, or benefits. For example, after a number of service years and reaching a specified salary or management level, top performers were invited to join the ELFUN society. Perks included additional investment opportunities in exclusive funds and ELFUNs were often tapped for roles in leading charitable and public service projects.
The actions built the teams and skills in the process. As a new manager, its often easy to rank the performers. Once you've worked with a team for a while and understand the consequences, its a lot harder to do the ranking. But this honed management and differentiation skills by forcing leaders to take deep dives into performance, strategy, and accomplishment. These deep dives fuel continuous improvement since managers were always helping people find ways to improve.
These actions created a culture of high performance. "Rank and file" employees rarely thought about it and unless you were in one of the extreme groups, you might not even know it was happening. But the results were there. There was no concept of "dead wood" or "hanging in there until something better comes along". The company was filled with high performers and employees were motivated. But all this came at a financial cost.
To support the system, there was a complete HR system which included job descriptions, salary divisions, robust performance criteria, detailed annual performance appraisals, goals and objectives, and frequent performance feedback. There was also the cost of bonuses, rewards, and perks scaled to the organization. Execution was relentless and strategies, goals, and tactics had to be devised and reviewed. Every player had to know their position and was slotted into positions where they could be most successful. There was also no guarantee you would be in the same group forever -- re-evaluation was an ongoing process. It was an unswerving dedication to continuous improvement of people and in the process, the entire organization.
The results were obvious every day. People had fun in their jobs. As a manager and project manager, I never had to worry about who would show up to work -- good people were always there. And those costs I mentioned -- they were usually offset by improved productivity and corporate performance. The Vitality Curve helped the company go from good to great.
This didn't mean there weren't tough times. While GE has always been a financial powerhouse, the economic forces are often more powerful. But with a solid performing team, recovery from setbacks is quicker and there was an understanding that the work had to continue. The people chattering in the halls about coming layoffs and hard times were often those few in the bottom 10% or those headed in that direction.
So while this might not be a concept for everyone, the GE vitality curve is a must for devotees of continuous improvement and high performing teams. If you are working on a long term (e.g. 5 year) project or program, you may want to consider starting a grass roots version to see if your team improves.
Tuesday, June 2, 2009
PMP® Challenge Question - 6/1
The question posed for today is "What does RACI stand for?"
RACI is a technique which can be used for creating a RAM or Responsibility Assignment Matrix. The letters stand for Responsible, Accountable, Consulted, and Informed. Some articles about RACI add "VS" for Verifies and Signs Off.
Well that one was easy!
Here's a question for 6/15:
What do we call the narrative description of services to be supplied as part of a contract?
Check back on 6/15 for the answer!
RACI is a technique which can be used for creating a RAM or Responsibility Assignment Matrix. The letters stand for Responsible, Accountable, Consulted, and Informed. Some articles about RACI add "VS" for Verifies and Signs Off.
Well that one was easy!
Here's a question for 6/15:
What do we call the narrative description of services to be supplied as part of a contract?
Check back on 6/15 for the answer!
Labels:
human resources,
PMP Challenge Question,
procurement
Friday, May 22, 2009
Expectations, RACI, and RACI-VS
Managing the expectations of a Project Team can often be more difficult than managing those of external stakeholders. Teams “form, storm, norm, and perform”, but short projects and critical tasks can be impacted by unwanted behaviors, especially if the team members don’t know what’s expected of them. RACI and RACI-VS are forms of a Responsibility Assignment Matrix (RAM) which can help focus the team on their roles and responsibilities while aiding the project manager in thinking through the Human Resources plan.
The PMBOK® Guide includes the Responsibility Assignment Matrix in the Human Resources plan. It is designed to show the connections between the work packages of the WBS and the project team. Multiples levels of RAM may be presented. A high level RAM may show connections between high level packages (such as project phases or summary tasks) and sub teams or generic resources. Ultimately the RAM connects each task to specific, named team members.

The illustrated RAM is a part of the Estimating Tool I developed. Planning is by role, effort, and week. This and other RAMs like it are still too general for some project teams. Another level of detail is possible when using the RACI (Responsible, Accountable, Consulted, and Informed) model.
The PMBOK® Guide suggests that a RACI model is important to describe the interface between multiple teams (e.g. buyer/seller, internal/external, product management/development/sales and marketing). Tasks on one axis, resources on another, the cells are filled in with one of the letters.
The PMBOK® Guide doesn’t provide any rules about creating RACI charts and there is little literature available, but a few things should pop out as common sense:
- Multiple “A”ccountable and unrelated resources can cause conflicts in differences of opinion. You should be sure the team members are co-chairs, co-leads, or at least in similar roles and will collaborate well together. Multiple A’s should be kept to a minimum.
- The “R”esponsible role defines who does the work.
- Multiple “R”esponsible can cause unnecessary or duplicate work. Make one team member responsible for each task.
- Keeping multiple people “I”nformed helps develop capacity. If a team member is absent or unable to carry out work for any reason, you have developed a successor for that role.
- Multiple “C”onsulted is desirable to collect input from all potential subject matter experts.
- In general, any team member should have only one role.
- If any column is empty, consider if that resource is necessary for the project.

RACI-VS is not in the PMBOK® Guide, however I did come across it in Wikipedia. Having worked with mature companies (SEI Level 3 and above), I can see the importance. Someone needs to quality assure, acceptance test, or otherwise confirm that a task is complete. The final sign off acts as a gate which prevents incomplete work from moving forward. The development environment at GE Information Services was a key example. Once a change was coded, each developer had to seek out a peer with subject matter expertise to review the code change. Feedback might include performance improvement suggestions, adherence to coding standards, unit testing suggestions, and other work that needed to be examined for integration. Once the verification was complete, the change was forwarded to management for sign off. The development manager might inquire about potential issues or the testing conducted prior to sign off.
Once again, some common sense rules should be considered:
- For many projects, the “S”ign off role might also be assigned to the “A”ccountable person to provide them an opportunity to ensure project standards are met and processes are followed.
- Too many “S”ign offs can cause delay as the work product is routed for review.
- “V”erification should be independent (e.g. an architect who created a change shouldn’t verify the change) where possible to insure the highest quality.
- “V”erification often designates the quality assurance or project scope
verification role.
- The verification and sign off roles may be in addition to other roles.
There are multiple ways the concepts of RACI and RACI-VS can be applied:
- They make ideal designations for roles and responsibilities in a process definition or chart.
- If you make R=Recommends and A=Approves, you have the foundation for a decision making process.
- CAIRO or RACI-O adds “O”ut-of-the-Loop as a role – someone who does not need to be involved in a task at all.
- RASCI adds “S”upport.
The PMBOK® Guide defines the Responsibility Assignment Matrix as part of the Human Resource plan for a project. They help the project manager set expectations for roles and responsibilities as well as plan the project resources. RACI and RACI-VS are forms of a RAM and may be multi-level in nature. They define who is responsible, accountable, consulted, informed, verifies, and signs off on project tasks. We looked at some common sense rules such as making sure only one person is responsible for each task to avoid redundant work or wasted effort. There are also multiple ways the concept can be applied and we looked at four different applications.
The PMBOK® Guide includes the Responsibility Assignment Matrix in the Human Resources plan. It is designed to show the connections between the work packages of the WBS and the project team. Multiples levels of RAM may be presented. A high level RAM may show connections between high level packages (such as project phases or summary tasks) and sub teams or generic resources. Ultimately the RAM connects each task to specific, named team members.

The illustrated RAM is a part of the Estimating Tool I developed. Planning is by role, effort, and week. This and other RAMs like it are still too general for some project teams. Another level of detail is possible when using the RACI (Responsible, Accountable, Consulted, and Informed) model.
The PMBOK® Guide suggests that a RACI model is important to describe the interface between multiple teams (e.g. buyer/seller, internal/external, product management/development/sales and marketing). Tasks on one axis, resources on another, the cells are filled in with one of the letters.
The PMBOK® Guide doesn’t provide any rules about creating RACI charts and there is little literature available, but a few things should pop out as common sense:
- Multiple “A”ccountable and unrelated resources can cause conflicts in differences of opinion. You should be sure the team members are co-chairs, co-leads, or at least in similar roles and will collaborate well together. Multiple A’s should be kept to a minimum.
- The “R”esponsible role defines who does the work.
- Multiple “R”esponsible can cause unnecessary or duplicate work. Make one team member responsible for each task.
- Keeping multiple people “I”nformed helps develop capacity. If a team member is absent or unable to carry out work for any reason, you have developed a successor for that role.
- Multiple “C”onsulted is desirable to collect input from all potential subject matter experts.
- In general, any team member should have only one role.
- If any column is empty, consider if that resource is necessary for the project.

RACI-VS is not in the PMBOK® Guide, however I did come across it in Wikipedia. Having worked with mature companies (SEI Level 3 and above), I can see the importance. Someone needs to quality assure, acceptance test, or otherwise confirm that a task is complete. The final sign off acts as a gate which prevents incomplete work from moving forward. The development environment at GE Information Services was a key example. Once a change was coded, each developer had to seek out a peer with subject matter expertise to review the code change. Feedback might include performance improvement suggestions, adherence to coding standards, unit testing suggestions, and other work that needed to be examined for integration. Once the verification was complete, the change was forwarded to management for sign off. The development manager might inquire about potential issues or the testing conducted prior to sign off.
Once again, some common sense rules should be considered:
- For many projects, the “S”ign off role might also be assigned to the “A”ccountable person to provide them an opportunity to ensure project standards are met and processes are followed.
- Too many “S”ign offs can cause delay as the work product is routed for review.
- “V”erification should be independent (e.g. an architect who created a change shouldn’t verify the change) where possible to insure the highest quality.
- “V”erification often designates the quality assurance or project scope
verification role.
- The verification and sign off roles may be in addition to other roles.
There are multiple ways the concepts of RACI and RACI-VS can be applied:
- They make ideal designations for roles and responsibilities in a process definition or chart.
- If you make R=Recommends and A=Approves, you have the foundation for a decision making process.
- CAIRO or RACI-O adds “O”ut-of-the-Loop as a role – someone who does not need to be involved in a task at all.
- RASCI adds “S”upport.
The PMBOK® Guide defines the Responsibility Assignment Matrix as part of the Human Resource plan for a project. They help the project manager set expectations for roles and responsibilities as well as plan the project resources. RACI and RACI-VS are forms of a RAM and may be multi-level in nature. They define who is responsible, accountable, consulted, informed, verifies, and signs off on project tasks. We looked at some common sense rules such as making sure only one person is responsible for each task to avoid redundant work or wasted effort. There are also multiple ways the concept can be applied and we looked at four different applications.
Thursday, April 2, 2009
PMP ® Challenge Question - 4/1
On March 15th, the challenge was:
You have finished project management training and desire to earn your PMP® credential. What are some constructive ways you can go about applying your new knowledge and obtaining your first project management assignment at your company?
Certainly one of your first steps might be a discussion with your manager. Let him/her know about your accomplishment and how you might be able to apply your knowledge in a work assignment. Your HR manager is another possible resource. Another constructive tactic might be to have a discussion with existing project managers in the company and ask if you can be considered for a role on a project team. If you have any additional ideas to share, please leave a comment or drop me a line at sdcapmp@aol.com.
Now for the new challenge. Here are some acronyms found in the procurement knowledge area. What does each stand for? Provide a brief sentence or two about what each is.
CR
CPFF
FPFT
CPRC
Good luck with the challenge!
You have finished project management training and desire to earn your PMP® credential. What are some constructive ways you can go about applying your new knowledge and obtaining your first project management assignment at your company?
Certainly one of your first steps might be a discussion with your manager. Let him/her know about your accomplishment and how you might be able to apply your knowledge in a work assignment. Your HR manager is another possible resource. Another constructive tactic might be to have a discussion with existing project managers in the company and ask if you can be considered for a role on a project team. If you have any additional ideas to share, please leave a comment or drop me a line at sdcapmp@aol.com.
Now for the new challenge. Here are some acronyms found in the procurement knowledge area. What does each stand for? Provide a brief sentence or two about what each is.
CR
CPFF
FPFT
CPRC
Good luck with the challenge!
Labels:
human resources,
PMP Challenge Question,
procurement
Sunday, March 15, 2009
PMP® Challenge Question - 3/15
On 2/15, the Challenge Question asked about RACI-VS. This is Responsible, Accountable, Consulted, Informed, Verifies, and Signs off. These are the key responsibilities which can be associated with a RAM or Responsibility Assignment Matrix.
Now for the next challenge. This is a human resources question:
You have finished project management training and desire to earn your PMP® credential. What are some constructive ways you can go about applying your new knowledge and obtaining your first project management assignment at your company?
See you April 1st!
Now for the next challenge. This is a human resources question:
You have finished project management training and desire to earn your PMP® credential. What are some constructive ways you can go about applying your new knowledge and obtaining your first project management assignment at your company?
See you April 1st!
Sunday, February 15, 2009
PMP® Challenge Question - 2/15
On 2/1 I asked:
An Earned Value Analysis for a recently closed out project revealed:
SPI = 0.7, CPI = 1.0
State at least THREE conclusions you can draw from this statement.
The statements are:
1) Cost is on target.
2) Schedule is over budget.
3) Project deliverables are complete (tricky ... but you are closing out the project)
Here's the next challenge:
What does RACI-VS stand for? For the project team, who is usually responsible/accountable for understanding how all the project tasks fit together?
See you on March 1!
An Earned Value Analysis for a recently closed out project revealed:
SPI = 0.7, CPI = 1.0
State at least THREE conclusions you can draw from this statement.
The statements are:
1) Cost is on target.
2) Schedule is over budget.
3) Project deliverables are complete (tricky ... but you are closing out the project)
Here's the next challenge:
What does RACI-VS stand for? For the project team, who is usually responsible/accountable for understanding how all the project tasks fit together?
See you on March 1!
Saturday, February 7, 2009
Moving on Up in Project Management
A recent PM Hut reader asked "I'm a PM at a small web developing company, but as soon as I can I want to work at a multinational company. I hope you can help me with that." The rest of the message asked three specific questions and also implied this was a move from a small to large environment. Having worked on both US coasts for companies as large as General Electric and as small as one employee, I thought I might be able to shed some light on this in general, as well as address the three questions. I broke the general case down into five specific categories:
Portable Skill Set
As a Project Manager, if you are adhering to the internationally recognized best practices of the Project Management Institute's PMBOK Guide®, you have developed a highly portable skill set which can be used across industries and companies. There is a bit of a "catch" -- the recent Value of Project Management study by the University of Athabasca found there is not one path to project management. As you embark on a new position, there will be a learning period for "local rules". Take the time to find out how they do project management, so you can identify areas where you can immediately contribute and others which might require some ramp up. If you don't have this skill set, visit Learn About PMI Certifications to get started.
Scalable
I often suggest to my project management students that they keep the "bureaucracy" proportional to the company size. A small one month project doesn't require a 50-page project plan and daily status reports. However a 10 year, global project may require something larger. Make sure the supporting tools and techniques you use in your management of projects scale to meet the circumstances.
Maturity of Project Management Practice
I've observed that larger companies often have more mature practices. This can be due to longevity (GE has been around for more than a century and started out small), funding for development, business needs, or continuous improvement, among other things. Reviewing tools such as Kerzner's Project Management Maturity Model and PMI's Organizational Project Management Maturity Model will help you in understanding your environment.
Cultural Sensitivity
For a multi-national company, be aware of how the people you will be dealing with think about time, costs, and doing business as this will impact your ability to control project costs and risks. Australians frequently go on summer "holiday". Some European cultures are know for long afternoon breaks, but late nights -- you may be able to catch someone in the office at 8pm in their time zone. In Japan, silence is usually not consensus, but disagreement or deferment to a higher authority. I don't want to "generalize" anyone, but this should give you a few things to think about and explore.
Support Systems
Larger environments tend to have more support systems in place. Find out how you can leverage these to your advantage. Very small companies, for example, are usually difficult to introduce to change control and earned value management. Larger companies may have the basics in place and you will be able to contribute to their continuous improvement.
Now let's take a look at the three specific questions this reader had:
1. Does the IT PM need to have a programming knowledge?
In general, to be a strong project leader, you should strive to become a subject matter expert. Now this doesn't necessarily mean you have to write code in a specific programming language, but you should develop general skills such as understanding the software project life cycle, how to evaluate and select programmers and programming environments, and other business and industry-related skills. You will be called upon to lead the discussions of estimates and plans, so it would help to have a general knowledge of how the pieces fit and how the estimates are derived.
2. None of us starts his/her career as a PM, so what are the previous positions I need to have before I become a PM at a multinational company?
There is no one path -- any path that helps you acquire the management and people skills to be a project manager will do. Large companies have management training programs, and I was fortunate enough to be able to attend some classes at GE's famous Crotonville management training facility. Find out if such a program is available to you, or investigate PM training or degrees at your local university. PMI members also have access to the PMI Career Framework.
3. What kind of skill do I need to get into that previous position?
Again, no one set answer, however I've always found a strong desire, development of personal goals, and continued demonstration of mastery of related skills to be a good path.
As always, reader questions are invited! Drop a line to sdcapmp@aol.com.
Portable Skill Set
As a Project Manager, if you are adhering to the internationally recognized best practices of the Project Management Institute's PMBOK Guide®, you have developed a highly portable skill set which can be used across industries and companies. There is a bit of a "catch" -- the recent Value of Project Management study by the University of Athabasca found there is not one path to project management. As you embark on a new position, there will be a learning period for "local rules". Take the time to find out how they do project management, so you can identify areas where you can immediately contribute and others which might require some ramp up. If you don't have this skill set, visit Learn About PMI Certifications to get started.
Scalable
I often suggest to my project management students that they keep the "bureaucracy" proportional to the company size. A small one month project doesn't require a 50-page project plan and daily status reports. However a 10 year, global project may require something larger. Make sure the supporting tools and techniques you use in your management of projects scale to meet the circumstances.
Maturity of Project Management Practice
I've observed that larger companies often have more mature practices. This can be due to longevity (GE has been around for more than a century and started out small), funding for development, business needs, or continuous improvement, among other things. Reviewing tools such as Kerzner's Project Management Maturity Model and PMI's Organizational Project Management Maturity Model will help you in understanding your environment.
Cultural Sensitivity
For a multi-national company, be aware of how the people you will be dealing with think about time, costs, and doing business as this will impact your ability to control project costs and risks. Australians frequently go on summer "holiday". Some European cultures are know for long afternoon breaks, but late nights -- you may be able to catch someone in the office at 8pm in their time zone. In Japan, silence is usually not consensus, but disagreement or deferment to a higher authority. I don't want to "generalize" anyone, but this should give you a few things to think about and explore.
Support Systems
Larger environments tend to have more support systems in place. Find out how you can leverage these to your advantage. Very small companies, for example, are usually difficult to introduce to change control and earned value management. Larger companies may have the basics in place and you will be able to contribute to their continuous improvement.
Now let's take a look at the three specific questions this reader had:
1. Does the IT PM need to have a programming knowledge?
In general, to be a strong project leader, you should strive to become a subject matter expert. Now this doesn't necessarily mean you have to write code in a specific programming language, but you should develop general skills such as understanding the software project life cycle, how to evaluate and select programmers and programming environments, and other business and industry-related skills. You will be called upon to lead the discussions of estimates and plans, so it would help to have a general knowledge of how the pieces fit and how the estimates are derived.
2. None of us starts his/her career as a PM, so what are the previous positions I need to have before I become a PM at a multinational company?
There is no one path -- any path that helps you acquire the management and people skills to be a project manager will do. Large companies have management training programs, and I was fortunate enough to be able to attend some classes at GE's famous Crotonville management training facility. Find out if such a program is available to you, or investigate PM training or degrees at your local university. PMI members also have access to the PMI Career Framework.
3. What kind of skill do I need to get into that previous position?
Again, no one set answer, however I've always found a strong desire, development of personal goals, and continued demonstration of mastery of related skills to be a good path.
As always, reader questions are invited! Drop a line to sdcapmp@aol.com.
Friday, December 26, 2008
What if the Holidays Aren't Happy
By: Susan Peterson, M.B.A., PMP
Copyright 2008, Susan Peterson, All Rights Reserved
Usually my December column has focused on managing projects through the seasonal abundance of joy that can accompany the year-end holidays. However, this year’s holiday season seems to be destined to be more heavily weighted toward gloom rather than toward mirth. “Doing more with less” is giving way to “doing something with nothing” on personal, organizational, and global fronts. Even a well-managed project can rapidly decline in effectiveness when the team members, sponsors, and other stakeholders are constantly bombarded with media reminders of the latest bad news. So with the hope that someday this era will be just a dim, bad memory, this month’s column provides some ideas for leading projects through bleak times.
Focus on success
It’s common at the end of the year to reflect on past events. Assuming that the project has accomplished the majority of its deliverables and met most of its milestones, it is a good time to highlight the major project successes. Rather than just focusing on the achievement of Gantt chart targets, the contributions of each team member and stakeholder can be highlighted across the accomplishments. This recognition can be made in a variety of methods, such as brief descriptions/photos on the project’s website, a special recognition meeting, or a potluck lunch. Funds for more elaborate forms of recognition may be nonexistent this year, but personal recognition is always a nice “present”.
Now some of you may be saying, “What success? My project budget was cut without warning, some of my team was laid off, and we’ve been told that any project could be terminated with or without advance notice.” There still were probably successes, however small, that demonstrated that heroic efforts paid off even in dire circumstances. In fact, sometimes it’s a morale booster to look back at projects that have been through survival mode and to be happily surprised at the level of accomplishments. Some people may even find that they no longer fear certain challenging situations such as having to drastically cut budgets because they know that they have been tested and have risen to the challenge.
When all else fails, there’s always work
This column section is not advocating that becoming a workaholic is a cure for depressing news. However, team members may welcome the need to dig into some intense, short duration tasks that require concentration or that provide mental stimulation. Perhaps there is some vendor assessment that needs to be conducted or a prototype design effort that requires input from multiple team members. The key is to plan activities in segments or phases that can be readily accomplished and that provide a series of opportunities for successes. It is also important to determine which activities are best performed by individuals versus those that will be more effectively completed with multiple personnel.
There are no quick fixes
While we might like to believe that taking two aspirin and getting a good night’s rest will make everything “right” immediately, the more plausible perspective is that recovery is not right around the corner. Rather than wasting energy on twisting with every “up and down”, project managers need to remain focused on project goals.
They also need to continue to assess how the project goals are aligning with changes that the organization may be making in this economic environment. Sometimes critical projects are shelved during declining times only to find later that those projects should have been continued even if they needed some modifications in order to remain relevant. For example, companies need to continue anticipating needs for new products and services. While budgets may be reduced for the foreseeable future, companies need to be ready to bring new offerings to market as economies rebound.
Let us all hope for a positive 2009!
Susan Peterson, M.B.A., PMP, is a consultant who manages diverse programs and projects in both the private and public sectors for individual organizations and consortia. She also conducts enterprise assessments of project portfolio management practices. An overview of her program and project specialties is available at http://www.pmi-sd.org; select “Resources” then “Consultants”. She teaches the Project Management Simulation capstone course in the University of California, San Diego, Project Management certificate program and is a member of the curriculum committee. She can be contacted at susanada@aol.com.
Copyright 2008, Susan Peterson, All Rights Reserved
Usually my December column has focused on managing projects through the seasonal abundance of joy that can accompany the year-end holidays. However, this year’s holiday season seems to be destined to be more heavily weighted toward gloom rather than toward mirth. “Doing more with less” is giving way to “doing something with nothing” on personal, organizational, and global fronts. Even a well-managed project can rapidly decline in effectiveness when the team members, sponsors, and other stakeholders are constantly bombarded with media reminders of the latest bad news. So with the hope that someday this era will be just a dim, bad memory, this month’s column provides some ideas for leading projects through bleak times.
Focus on success
It’s common at the end of the year to reflect on past events. Assuming that the project has accomplished the majority of its deliverables and met most of its milestones, it is a good time to highlight the major project successes. Rather than just focusing on the achievement of Gantt chart targets, the contributions of each team member and stakeholder can be highlighted across the accomplishments. This recognition can be made in a variety of methods, such as brief descriptions/photos on the project’s website, a special recognition meeting, or a potluck lunch. Funds for more elaborate forms of recognition may be nonexistent this year, but personal recognition is always a nice “present”.
Now some of you may be saying, “What success? My project budget was cut without warning, some of my team was laid off, and we’ve been told that any project could be terminated with or without advance notice.” There still were probably successes, however small, that demonstrated that heroic efforts paid off even in dire circumstances. In fact, sometimes it’s a morale booster to look back at projects that have been through survival mode and to be happily surprised at the level of accomplishments. Some people may even find that they no longer fear certain challenging situations such as having to drastically cut budgets because they know that they have been tested and have risen to the challenge.
When all else fails, there’s always work
This column section is not advocating that becoming a workaholic is a cure for depressing news. However, team members may welcome the need to dig into some intense, short duration tasks that require concentration or that provide mental stimulation. Perhaps there is some vendor assessment that needs to be conducted or a prototype design effort that requires input from multiple team members. The key is to plan activities in segments or phases that can be readily accomplished and that provide a series of opportunities for successes. It is also important to determine which activities are best performed by individuals versus those that will be more effectively completed with multiple personnel.
There are no quick fixes
While we might like to believe that taking two aspirin and getting a good night’s rest will make everything “right” immediately, the more plausible perspective is that recovery is not right around the corner. Rather than wasting energy on twisting with every “up and down”, project managers need to remain focused on project goals.
They also need to continue to assess how the project goals are aligning with changes that the organization may be making in this economic environment. Sometimes critical projects are shelved during declining times only to find later that those projects should have been continued even if they needed some modifications in order to remain relevant. For example, companies need to continue anticipating needs for new products and services. While budgets may be reduced for the foreseeable future, companies need to be ready to bring new offerings to market as economies rebound.
Let us all hope for a positive 2009!
Susan Peterson, M.B.A., PMP, is a consultant who manages diverse programs and projects in both the private and public sectors for individual organizations and consortia. She also conducts enterprise assessments of project portfolio management practices. An overview of her program and project specialties is available at http://www.pmi-sd.org; select “Resources” then “Consultants”. She teaches the Project Management Simulation capstone course in the University of California, San Diego, Project Management certificate program and is a member of the curriculum committee. She can be contacted at susanada@aol.com.
Monday, December 15, 2008
PMP® Challenge Question - 12/15
It's time for another PMP Challenge Question giveaway. For the first reader to successfully email a correct response to two of the next three challenge questions, I have the following gift:
Emotional Intelligence for Project Managers – The People Skills You Need to Achieve Outstanding Results by Anthony Mersino, PMP.
So without further ado, here is the question:
Your project management team includes multipe external consultants from different companies. You find that repeated conflicts between the these consultants are slowing down project progress and jeopardizing the success of the project.
Given this situation, what stage of team development are you in?
Emotional Intelligence for Project Managers – The People Skills You Need to Achieve Outstanding Results by Anthony Mersino, PMP.
So without further ado, here is the question:
Your project management team includes multipe external consultants from different companies. You find that repeated conflicts between the these consultants are slowing down project progress and jeopardizing the success of the project.
Given this situation, what stage of team development are you in?
Labels:
human resources,
PMP Challenge Question
Saturday, July 19, 2008
Lead at a Higher Level
This past week I was visiting clients and partners in Southern California and Maryland/DC which provided me the opportunity to finish reading the Blanchard organizations book, Leading at a Higher Level. There is a strong message in here for those of us with project management clients, whether they be internal or external.
Like our triple constraint, Blanchard now points out the "triple bottom line" which companies and consultants need to keep an eye on: being the provider of choice, being the employer of choice, and being the investment of choice. Paying attention to these triples pays dividends in creating high performing organizations. The book sums it up with a quote:
With increased global and local competition, fueled by economic issues (pun intended), customers have become more demanding. Like the old Burger King commercials, they now want it their way, meaning how they want it, when they want it, and at the price they expect. This goes way beyond customer satisfaction -- we need to create raving fans who crave our services. Again, its summed up with a short quote:
Taking care of your employees is as important as taking care of your customers. How many times have you found overworked, under-empowered employees with poor attitudes? This poor attitude gets passed on to customers, impacting business. You also need to ensure you have the right employees -- those with the necessary skills and attitudes to ensure your customers are handled properly.
Being the investment of choice doesn't just mean finding those who will buy stock or make direct investments. This includes customer contracts -- if you treat your employees right, do the best work you can, and serve customer needs, they will want to make further investment by returning to you for more work.
Want more information on creating high performing teams and organizations? I suggest you pick up a copy of this book for strategies, tactics, and tips from the best minds at Ken Blanchard Companies.
Like our triple constraint, Blanchard now points out the "triple bottom line" which companies and consultants need to keep an eye on: being the provider of choice, being the employer of choice, and being the investment of choice. Paying attention to these triples pays dividends in creating high performing organizations. The book sums it up with a quote:
Profit is the applause you get for taking care of your customers and creating a motivating environment for your people.
With increased global and local competition, fueled by economic issues (pun intended), customers have become more demanding. Like the old Burger King commercials, they now want it their way, meaning how they want it, when they want it, and at the price they expect. This goes way beyond customer satisfaction -- we need to create raving fans who crave our services. Again, its summed up with a short quote:
If you don't take care of your customers, somebody else will.
Taking care of your employees is as important as taking care of your customers. How many times have you found overworked, under-empowered employees with poor attitudes? This poor attitude gets passed on to customers, impacting business. You also need to ensure you have the right employees -- those with the necessary skills and attitudes to ensure your customers are handled properly.
Being the investment of choice doesn't just mean finding those who will buy stock or make direct investments. This includes customer contracts -- if you treat your employees right, do the best work you can, and serve customer needs, they will want to make further investment by returning to you for more work.
Want more information on creating high performing teams and organizations? I suggest you pick up a copy of this book for strategies, tactics, and tips from the best minds at Ken Blanchard Companies.
Labels:
human resources,
leadership,
project management
Friday, May 2, 2008
MBWA - Healthy, Wealthy, and Wise
Management by Walking Around is the healthy, wealthy, and wise choice for the ages. Well, at least in 2008 as stress increases with more to do and economic stress. According to the Moores Cancer Center at UCSD, committing to daily physical activity is an important preventative measure for cancer. Their web site states: "Aim for at least 10,000 steps each day, including moderate intensity activity such as brisk walking. Wear a pedometer to help you monitor your steps. (breast, lung, prostate, colon, endometrial cancers)." With more to do, many of us find it harder and harder to find the time to exercise. Management by Walking Around keeps us active and away from our desks at least a part of the time and will supplement other activities.
Its also a wise choice because it helps us get more done. Brief social and professional interactions refresh the mind and spirit. Studies have also shown the attention doesn't hurt in reminding our colleagues of our agendas while taking the time to genuinely listen to theirs. Push the chair back from the keyboard, stop sending emails to people across the hall, and spend a few minutes to get up and interact with them.
As far as wealthy, well there are never guarantees, but as the management team notices the improvements, one would hope there would be something in it for everyone!
Its also a wise choice because it helps us get more done. Brief social and professional interactions refresh the mind and spirit. Studies have also shown the attention doesn't hurt in reminding our colleagues of our agendas while taking the time to genuinely listen to theirs. Push the chair back from the keyboard, stop sending emails to people across the hall, and spend a few minutes to get up and interact with them.
As far as wealthy, well there are never guarantees, but as the management team notices the improvements, one would hope there would be something in it for everyone!
Saturday, March 29, 2008
Its People that Cause Problems
Not too long ago I had a project sponsor relate to me the need for "real time data" so their projects could be effectively managed. That one took a little while to digest and further examination showed issues at multiple levels which real time data was not going to solve. People issues were at the center of it.
First, it turned out that accounting data was only available on a monthly basis and there is no interface for on-the-spot reviews. Getting the right information at the right intervals can be invaluable. I generally recommend having the most recent data available on demand and having status updates no less than weekly. You may recall from previous posts that a weekly trip to the accounting department (not necessarily always the same day or time) generated sufficient information to provide an earned value report. While results may vary depending on project and circumstances, real time usually isn't required. There was a long standing request for "on demand" data, but that could be traced back to a people/resources issue in that it wasn't fulfilled.
The next related issue was gleaned from the accounting data. Bottom line -- there were inefficiencies in the organization which required correction. This is something the Project Manager (and often the project sponsor) cannot address. Its the role of functional and/or senior management to correct. Here again, the issue had been made known, but there was no action for a lengthy period of time. The best the Project Manager and project sponsor can do in these circumstances is escalate the issue again for resolution.
It often becomes convenient in our electronic world to blame "systems" and "process" for failures. Usually if we look deeper, we can find people related issues at the core. Our ability to solve these issues is aided by having clear roles and responsibilities as well as having the right people for the right tasks. These types of issues can often be deep rooted and take longer to solve, but by working on these we can resolve root cause and make future projects run smoother.
First, it turned out that accounting data was only available on a monthly basis and there is no interface for on-the-spot reviews. Getting the right information at the right intervals can be invaluable. I generally recommend having the most recent data available on demand and having status updates no less than weekly. You may recall from previous posts that a weekly trip to the accounting department (not necessarily always the same day or time) generated sufficient information to provide an earned value report. While results may vary depending on project and circumstances, real time usually isn't required. There was a long standing request for "on demand" data, but that could be traced back to a people/resources issue in that it wasn't fulfilled.
The next related issue was gleaned from the accounting data. Bottom line -- there were inefficiencies in the organization which required correction. This is something the Project Manager (and often the project sponsor) cannot address. Its the role of functional and/or senior management to correct. Here again, the issue had been made known, but there was no action for a lengthy period of time. The best the Project Manager and project sponsor can do in these circumstances is escalate the issue again for resolution.
It often becomes convenient in our electronic world to blame "systems" and "process" for failures. Usually if we look deeper, we can find people related issues at the core. Our ability to solve these issues is aided by having clear roles and responsibilities as well as having the right people for the right tasks. These types of issues can often be deep rooted and take longer to solve, but by working on these we can resolve root cause and make future projects run smoother.
Friday, October 26, 2007
Working with Remote Teams
For many years I worked with remote colleagues around the world. While with GE Information Services I worked with folks in Europe. With Siebel Systems my PMO colleagues were around the globe in Mexico, Europe, Australia, and around the US. Quarterly face-to-face meetings and regular conference calls kept the team in sync. Things went very smoothly since we all were professionals and worked for the same company.If you need to work with remote teams and everyone isn't a part of a common organization, it may be a little more difficult. As the PM, it may be difficult to know if the team is really moving forward with your project. Here are a few things to keep in mind for managing the virtual team:
- There may be language and cultural barriers, so there may be a need to be very explicit about expectations and requirements.
- Regular face-to-face meetings may be necessary -- you will need to determine the interval.
- It's important to have clear deliverables at shorter intervals.
- If you are conducting an agile project, leading edge communications and collaboration technology will be essential.
- Have a clear communications plan. You may also be able to take advantage of time zone differences to "tag-team" issues around the clock.
- Make sure the right people are on the team. It's easier if everyone is dedicated and really wants to be a part of the project.
- Share knowledge. This might range from archiving emails for orientation of new people to a knowledge management system.
Have more tips on managing virtual teams? Leave them in comments or email to sdcapmp@aol.com. Don't forget, the deadline for answering the PMP Challenge Questions for a PMP Exam Prep book and CD is just a few days away!
Labels:
human resources,
PMP Challenge Question
Saturday, March 31, 2007
Scale the Bureaucracy

Typewriters are gone. Yet this week I saw one of those "automatic" carbon forms -- a form in triplicate. These are all but extinct too. But it was an important reminder of a lesson learned for me -- scale your project bureacracy to fit the size of the project team.
Why is this important? If you and your team number six, and there is you and four team leads, you may find yourself short of team members to carry out the work. This is especially true if the team leads have to fill out daily logs, timecards, status reports, and forms, forms, forms, in triplicate. Project governance time shouldn't outweigh the project work time.
Before suggesting the addition of another team lead or adding more bureaucracy, take a look at some basic prinicples for guidance:
- The average management span of control is 7-10 and a team lead should be able to handle 4-6. This needs to be examined in light of the work performed.
- Look at the work time and responsibilities of your leaders; "oversite" time should be less than "leading" time. On one project where I had three groups of 10 people working in different areas, one "supervisor" was appointed for each group to make sure things moved along smoothly.
- Always look for ways to reduce "administrivia". GE Workout or just a lead and lag time analysis are good ways to perform this analysis.
- Find project team members who are enthusiastic about fulfilling their roles and who want to always do their best work -- they will require far less supervision than someone who is just along for the ride.
- Require managers and leads to perform project work as well. Make sure the management responsibilities add value. Team leads and similar positions should be spending only 25% of their time managing. Line managers may need 50% of their time to manage and only senior directors and VPs need to focus 100% of their effort on management tasks. These are just rules of thumb.
- Even small companies can benefit from these suggestions. Frequently they want to add management layers and titles to make everyone feel promoted, but the management and title heavy culture will be difficult to change later.
So to get things done, be the one to cut through red tape and management overhead. Scaling the bureaucracy will help you and your teams be more effective.
Saturday, February 17, 2007
Get Motivated!
This week I had the pleasure of taking my team to Peter Lowe's Get Motivated! seminar. It was a great opportunity for low cost, high value professional development. A cross between an Amway meeting, a Bible revival, an infomercial, and a seminar, the day was packed with usable information on success, leadership, tools to manage your personal finances, and sales closing. The knowledge and wisdom in these areas came from Krish Dhanam, Zig Ziglar (now 80 years old!), Steve Forbes, Phil Town, Marty Schottenheimer, Tom Hopkins, LaDainian Tomlinson (better known as LT to San Diego Chargers fans), and presidential candidate and former 2001 Time Man of the Year, Rudy Giuliani.
Even those with additional seminars to sell, like Tom Hopkins, had great things to say. Tom encouraged the audience to treat failure as a learning experience and change their attitude to the word "no". Does this sound in line with the theme of this blog? His "Champion Creed" is "I am not judged by the number of times I fail, but by the number of times I succeed."
Rudy Giuliani had these seven things for leaders to work on:
1. Have strong beliefs
2. Be an optimist
3. Have courage
4. Relentless preparation (if you anticipate everything you can, you can plan the unanticipated!)
5. Teamwork
6. Communication
7. Love people
There was plenty here for project managers, leaders, sales people, and anyone who wanted to hear more on these topics. It was well worth the cost. Be sure to check them out if they visit your city.
Even those with additional seminars to sell, like Tom Hopkins, had great things to say. Tom encouraged the audience to treat failure as a learning experience and change their attitude to the word "no". Does this sound in line with the theme of this blog? His "Champion Creed" is "I am not judged by the number of times I fail, but by the number of times I succeed."
Rudy Giuliani had these seven things for leaders to work on:
1. Have strong beliefs
2. Be an optimist
3. Have courage
4. Relentless preparation (if you anticipate everything you can, you can plan the unanticipated!)
5. Teamwork
6. Communication
7. Love people
There was plenty here for project managers, leaders, sales people, and anyone who wanted to hear more on these topics. It was well worth the cost. Be sure to check them out if they visit your city.