On 2/1 I asked:
An Earned Value Analysis for a recently closed out project revealed:
SPI = 0.7, CPI = 1.0
State at least THREE conclusions you can draw from this statement.
The statements are:
1) Cost is on target.
2) Schedule is over budget.
3) Project deliverables are complete (tricky ... but you are closing out the project)
Here's the next challenge:
What does RACI-VS stand for? For the project team, who is usually responsible/accountable for understanding how all the project tasks fit together?
See you on March 1!