There were no correct responses to the last challenge question, so I'll hold those questions for future use. Here's a fresh question to start off February:
An Earned Value Analysis for a recently closed out project revealed:
SPI = 0.7, CPI = 1.0
State at least THREE conclusions you can draw from this statement.
See you on 2/15 with the correct answer!